Karnataka govt. to invest on Hassan airport, even as operations face uncertainty in other district airports
Shivamogga The Karnataka Cabinet has decided to expand the Hassan airport project at a time when flight operations at other airports, including Shivamogga, face an uncertain future. An airport for Hassan has been in the pipeline for several decades. Incidentally, Star Air, the private operator, ended its flights from Shivamogga Airport under the UDAN scheme on Friday (November 20, 2026), as the three-year subsidy period came to an end.
The airline will continue to take bookings for the weekend on the Hyderabad route only, at commercial fares, without subsidy. Last flights under UDAN to take off from Shivamogga today storyline 1 On Thursday, the Cabinet approved a revised cost of ₹542.96 crore for the project, up from the ₹193.65 crore sanctioned in 2021. It cleared an additional ₹349.31 crore, of which ₹122 crore is for acquiring more land and ₹227.31 crore for additional works and the facilities needed to operate the airport.
Political push Excise Minister and Hassan in-charge Minister K.M. Shivalinge Gowda has held meetings to speed up land acquisition, which has held up the work. He has said he aims to start flights from Hassan within two years and to inaugurate the airport before his term ends. The demand for an airport in Hassan, about 190 km from Bengaluru, goes back more than six decades. Work has progressed at a snail’s pace, though land acquisition began as early as 1966.
Work on the ground began in 2021 but has shown hardly any progress in the last two years. The first proposal for the airport was prepared by the Central Public Works Department in 1960. In November 1966, 31 acres 31 guntas of private land and 58 acres of government land were acquired for the project. In the second phase, another 12 acres of private land and 42 acres of government land were acquired in 1971.
The project received attention during the JD(S)-BJP coalition government headed by H.D. Kumaraswamy. Former Prime Minister H.D. Deve Gowda laid the foundation stone in 2007, after the government signed an agreement with Jupiter Aviation Services Pvt. Ltd. for construction on the build-own-operate-transfer (BOOT) model. Agreement cancelled However, the work did not move forward.
The project proponent had planned additional activities, including a golf course and a hotel, and refused to start work until the entire 960 acres required for the project was handed over. The agreement with the private firm was cancelled in 2018, when the JD(S) came to power again, this time with the Congress. When B.S. Yediyurappa became Chief Minister, he announced ₹175 crore for the airport in his 2021 budget.
The Karnataka State Industrial Infrastructure Development Corporation (KSIIDC) was the project implementing agency. The project has now been revised. Meanwhile, KSIIDC Chairman S.G. Nanjayyanamath questioned the viability of airports in tier-II and tier-III cities such as Hassan and Raichur. Hassan is only two-and-a-half to three hours from Bengaluru by road, he noted, and asked whether people would choose to fly such a short distance.
He raised similar doubts about Raichur. “I am not opposed to constructing airports in these cities. But I wish there were a discussion on the viability of investing so much money in such projects,” he said during a recent visit to Shivamogga. Eom/ (Hassan airport photos available)