Adani project work on at village not listed in clearance: Official
MUMBAI: Amid a row over work on Adani Green Energy Ltd’s (AGEL) 1,500MW Tarali pumped storage project beginning in Satara’s Patan taluka despite lack of approval from National Board for Wildlife (NBWL), the state forest department’s honorary wildlife warden for the district has written to Maharashtra Pollution Control Board (MPCB) alleging that large-scale excavation and construction is underway in Sawarghar village, which was not listed on the environmental clearance (EC) granted by the Union forest ministry on Feb 11 last year.The honorary wildlife warden, Rohan Bhate, said the EC specified only four villages that stand to be affected—Nivade, Tondoshi, Kalambe and Jalu—in the district.A spokesperson from Adani Group said the EC covers the four villages as well as Dafalwadi, and the company later purchased private land in Sawarghar to set up temporary accommodation for workers.
The company said such an accommodation was included in the project layout approval from Central Electricity Authority. It said the project has all the relevant clearances and initial works are in progress at the site.The Tarali project, estimated at Rs 5,675 crore, is planned over 150.7 hectares of private land.In his letter to MPCB member-secretary Rahul Rekhawar, Bhate claimed that the activity in Sawarghar did not have the required EC and NBWL’s approval, and sought urgent intervention and an independent investigation.Rekhawar confirmed that MPCB has received Bhate’s letter and said it is investigating the allegations.Amol Satpute, MPCB sub-regional officer in Satara, said a team from the pollution regulator inspected the Sawarghar site on Friday, where excavation was underway.
Satpute said when officials questioned the site supervisor, they were told the developer was levelling land to set up a labour camp for the Tarali project. He said a report would be submitted to higher authorities.Bhate said the situation raised questions about the geographical scope and validity of the EC in relation to the work being carried out at Sawarghar. He questioned whether MPCB had verified that the proponent had obtained environmental and wildlife clearances for all land parcels involved before issuing the mandatory ‘consent to establish’ (CTE) that allows construction to begin.
He said MPCB cannot distance itself from responsibility because the CTE stage is a crucial regulatory checkpoint.Bhate requested an immediate site inspection and preparation of an official panchnama by MPCB officials to document the extent of excavation and construction, the machinery deployed, and the exact location of the work. He said if any excavation or construction is found to have started without statutory approvals, authorities should register the appropriate offence and initiate legal proceedings against responsible individuals and project authorities.He also asked MPCB to determine whether activity at Sawarghar is covered by the Feb 11, 2025, EC and whether all applicable environmental permissions for that specific location have been obtained.
In addition, he sought verification of whether prior approval from the NBWL’s standing committee was secured wherever legally required.Bhate said the proposed project falls within the deemed eco-sensitive zone of Koyna wildlife sanctuary and the Sahyadri tiger reserve, making strict scrutiny under environmental and wildlife protection provisions essential. He requested that the matter be assigned to an impartial higher-level authority for an independent inquiry rather than being examined only by officials linked to project clearances.
Pending verification, he asked for directions to prevent any further unauthorised excavation or construction at the site.Sources said AGEL has not yet complied with the stop-work order issued on Nov 13 by Satpute, in his capacity as the Satara division’s deputy conservator of forests, for starting work on the project without NBWL’s approval. Adani Group had earlier said the proposal had been submitted to NBWL.
Satpute said he would need to check whether the developer had followed the order.You Can Also Check: Gold Rate in Mumbai | Silver Rate in Mumbai | Bank Holidays in Mumbai | Public Holidays in Mumbai | Mumbai AQI | Weather in Mumbai | Petrol Price in Mumbai | Diesel Price in Mumbai | CNG Price in Mumbai | LPG Price in MumbaiStay updated with the latest Mumbai news. Download the TOI App.