DOSS MUSIC HOSTS GRAND STAR-STUDDED LAUNCH OF MISS UNIVERSE IN MUMBAI!DANICS Officer Abhishek Vyas Emerges Winner in Officers Voice 2026Women play a crucial role in the all-round development of the nation: Shilpa NayyarFrom Begging Bowls to Books: Dr. Kamal Saxena’s Mission to Rewrite ChildhoodsSULTAN MIRZA TRAILER UNVEILED WITH GREAT FANFARE; DIRECTOR IQBAL BAKSH AND PRODUCER HIMAYAT ALI GEAR UP FOR A GRAND DECEMBER RELEASE250-Crore Legal Battle: Pyare Khan Takes VHP and Bajrang Dal Members to CourtAkola MLA Sajid Khan Pathan to Sponsor 80% of Women's Skill Training Fees; Spoton Global Group Targets 1 Crore WomenA Changing Scenario: Something Good Is Happening in the Community with Spoton GlowVibe Entertainment Unveils Three Music Videos and Announces Four Upcoming FilmsVeteran Journalist Ram Bahadur Rai Turns 80, Rajnath Singh Attends Grand CelebrationASHOK VAJPEYI CONFERRED THE SHRIKANT VERMA SHIKHAR SAMMANHonouring Ancestors Through the Bhagwat: Pandit Shubham Agnihotri on an Enduring Spiritual TraditionDOSS MUSIC HOSTS GRAND STAR-STUDDED LAUNCH OF MISS UNIVERSE IN MUMBAI!DANICS Officer Abhishek Vyas Emerges Winner in Officers Voice 2026Women play a crucial role in the all-round development of the nation: Shilpa NayyarFrom Begging Bowls to Books: Dr. Kamal Saxena’s Mission to Rewrite ChildhoodsSULTAN MIRZA TRAILER UNVEILED WITH GREAT FANFARE; DIRECTOR IQBAL BAKSH AND PRODUCER HIMAYAT ALI GEAR UP FOR A GRAND DECEMBER RELEASE250-Crore Legal Battle: Pyare Khan Takes VHP and Bajrang Dal Members to CourtAkola MLA Sajid Khan Pathan to Sponsor 80% of Women's Skill Training Fees; Spoton Global Group Targets 1 Crore WomenA Changing Scenario: Something Good Is Happening in the Community with Spoton GlowVibe Entertainment Unveils Three Music Videos and Announces Four Upcoming FilmsVeteran Journalist Ram Bahadur Rai Turns 80, Rajnath Singh Attends Grand CelebrationASHOK VAJPEYI CONFERRED THE SHRIKANT VERMA SHIKHAR SAMMANHonouring Ancestors Through the Bhagwat: Pandit Shubham Agnihotri on an Enduring Spiritual Tradition
Mumbai family pay EMIs for undelivered flat; builder ordered to pay Rs 83 lakh
Latest News

Mumbai family pay EMIs for undelivered flat; builder ordered to pay Rs 83 lakh

27 Nov 2026, 09:18 AM 4 min read

MUMBAI: Holding that "financial insufficiency on the part of the developer cannot, by itself, justify such prolonged delay", the Additional District Consumer Disputes Redressal Commission, Mumbai Suburban, directed a builder to pay about Rs 83.56 lakh — including refund, interest, compensation and costs — for failing to deliver possession of a flat in Mulund West on time.In its order, the commission rejected the implied defence that the delay was due to funding issues, raised by M/s Riddhi Sidhi Corporation and its partners, Parveen Chamaria and Chetan Bhanushali.

It directed them to pay the amount, calculated as of Nov 2, 2026, to the Ghatkopar-based flat buyers, Mohan Anarse, Akash Anarse and Sunita Anarse. The commission added that the complainants "cannot be expected to wait indefinitely for completion of the project, particularly when there is no certainty regarding delivery of possession."The commission ordered a refund of Rs 52.80 lakh with simple interest at 9% per annum from July 31, 2020, until realisation.

Calculated up to the date of the order, the interest amounts to about Rs 29.75 lakh. The commission also awarded Rs 75,000 for mental agony, inconvenience and financial hardship, and Rs 25,000 towards litigation costs.“The evidence establishes that the Complainants invested a substantial amount in the purchase of the subject flat and continued to bear the financial burden of the housing loan without receiving possession.

They have consequently suffered mental agony, inconvenience and financial hardship. Hence, we find it appropriate to award compensation of Rs 75,000 towards mental agony and inconvenience,” the commission said.The complainants had booked Flat No. 1902, measuring 313.45 sq ft in carpet area, on the 19th floor of Wing F in the proposed Excellente project at Mulund West, Mumbai. The agreement for sale was executed on Feb 14, 2019, for a total consideration of Rs 69.14 lakh.

Under the agreement, possession was to be offered on or before July 31, 2020.The commission noted that “despite expiry of the stipulated period, the opposite parties failed to complete the construction and hand over possession.” It further observed that the evidence showed that only about 50% to 60% of the construction had been completed by the time the complaint was filed and that construction activity had stopped.The complainants said the flat was booked under a subvention scheme, under which EMIs were expected to begin only after possession.

However, due to the delay, they had to start paying EMIs from August 2020. The record showed that they had paid Rs 4.35 lakh from their own funds on Dec 25, 2018, and another Rs 25 lakh on Jan 22, 2019. The commission also found that the housing finance institution had disbursed Rs 23.45 lakh towards the flat.The opposite parties did not appear despite being served notice, and the matter proceeded ex parte.

The complainants had issued a legal notice on May 12, 2022, seeking cancellation of the agreement and a refund with interest. However, no refund was made.The commission held that the complainants were entitled to terminate the transaction. “In view of the failure of the opposite parties to complete the construction and deliver possession within the stipulated period, without establishing any justifiable reason for the delay, we hold that the opposite parties have committed deficiency in service,” it said.The order directed that the Rs 23.45 lakh disbursed by the financial institution, along with proportionate interest, be dealt with in coordination with the lender and adjusted against the housing loan after verification.

The remaining amount, along with proportionate interest, is to be paid directly to the complainants.The commission directed the builder and his partners to comply with the order within 45 days of receiving it. After the payment and adjustment, the parties must coordinate with the financial institution to obtain its consent, secure the release of the charge or mortgage, if applicable, and execute and register a deed cancelling the Feb 14, 2019, agreement for sale.You Can Also Check: Gold Rate in Mumbai | Silver Rate in Mumbai | Bank Holidays in Mumbai | Public Holidays in Mumbai | Mumbai AQI | Weather in Mumbai | Petrol Price in Mumbai | Diesel Price in Mumbai | CNG Price in Mumbai | LPG Price in MumbaiStay updated with the latest Mumbai news.